Wednesday 4 June 2014

Welcome to the Orchard Park Blog!

We are currently in the process of building 36 Houses and 16 Apartments for Riverside and Hull City Council in Orchard Park, Hull.
 
The purpose of the blog is to keep all the residents within the surrounding area as up to date as possible with the on-goings and progress of the build along with any changes to the nearby roads and pedestrian footpath that may occur throughout the project.
 
The bulk excavation works are almost complete with all of the plots complete ready for piling.
 
At the moment the foundations are being formed using a pile and ground beam system to support the houses and apartments.
 
Along with the foundations, the underground drainage is also being installed to the plots which are most complete ready for the beam and block floor to be laid above it.


 

Wednesday 14 May 2014

Important Notice...

May we firstly say thank you for your co-operation and understanding during the first few months of the contract on our site at Homethorpe, Orchard Park. We have completed the initial site set up, secured the area, and started work on the construction of the 52 new homes we are providing in conjunction with Riverside and Hull City Council.

We will be commencing with the piling works on Wednesday 14 May 2014.  These works will be ongoing for the next 6 weeks, from Monday to Friday between the hours of 8.00 am through to 5.00 pm.  During this time there may be more noise from site than usual.

We do apologise in advance for any inconvenience caused, and we will endeavour to carry out these works as quickly as possible.

Please feel free to call into our site should you experience any site related problems during our construction period.